project statys delivery

Project Overview

We are building a new screened Combined Sewer Overflow (CSO) in Geilston Park, Cardross to alleviate internal sewer flooding during periods of extreme weather.

At A Glance

  • Sewer flooding alleviation in properties, park and surrounding streets
  • Work starting Monday 20 May 2024 and expected to take approximately nine months to complete
  • £1.5million project being delivered by Caledonia Water Alliance

What We Are Doing

We are constructing a new screened Combined Sewer Overflow (CSO) in Geilston Park Cardross and upgrading the associated sewer network to alleviate sewer flooding in the area. Excess waste water will be discharged into the nearby Geilston Burn during storms.

A Combined Sewer Overflow – or CSO – is designed to prevent the contents of a sewer from backing up into homes and businesses during periods of extreme weather. They are a critical component required to manage flows during peak rainfall. 

Approximately 99% of CSO discharges are comprised of excess rain/surface water and domestic waste water (from sinks, showers, baths etc). Less than 1% is actually waste water from toilets.

 
Drone image of Cardross Park with Scottish Water's site at the bottom and the sea at the top.

Park Project

The work is being carried out in Geilston Park but will have wider benefits for Cardross

Why We Are Doing It

There is not enough capacity in the Cardross sewer network which has led to sewer flooding affecting nearly a dozen properties. Geilston Park and the tennis courts have also been affected.

Several potential solutions were considered but a new CSO is the best option to find a safe and more practicable route to divert excess rainwater away from the sewer network to reduce the risk of flooding.

The project will provide protection for the community with the minimum impact both during and after construction and also on the environment.

Drone image of Cardross Park with construction site surrounding playpark.

Geilston Park

Cardross CSO and Sewer Upgrade

How a CSO works

Update August 2024

Work is progressing on schedule, and we are now about to start installing the underground Combined Sewer Overflow (CSO) chamber in the Village Park.

On Wednesday 14 August we will begin gently driving metal sheet piles into the ground to allow us to excavate safely. The work will be monitored for vibration and noise levels and is expected to take two days.

Installation of the concrete chamber for the new CSO will then begin. Once completed, this will safely divert storm water down an upgraded sewer pipe to a newly constructed outfall during extreme weather.

Cardross CSO and Sewer Upgrade

Storm water will be diverted to a new outfall in extreme weather

Cardross CSO and Sewer Upgrade

Work is progressing well installing the new updated sewer and outfall