project statys delivery

Project Overview

We are committed to supporting sustainable economic growth, meeting the demand of new housing development.

This £2million project will see over a mile of new water main installed to provide a reliant and resilient supply to customers in an area of North Glasgow where over 5,000 new properties are being built or planned.

 

At a Glance

  • £2million investment
  • Project will be delivered in a series of phases over approximately six months
  • Our delivery partner George Leslie Ltd is carrying out the work

Robroyston Water Main Upgrade

Supporting Growth

The investment will support the connection of approximately 5000 new homes in the area.

What We Are Doing

The project involves upgrading key pieces of infrastructure and installing over 1600 metres of new, upgraded water main in Springburn and Robroyston in Glasgow. More details on each phase of the project can be found below.

Why We Are Doing It

We are committed to supporting sustainable economic growth - both domestic and commercial - to achieve the Scottish Government's strategic aim of a flourishing Scotland.

This is an important project to facilitate the growth of new housing in the area - particularly in Robroyston – that will ensure the reliance and resilience of the water supply to customers.

Robroyston Water Main Upgrade

Phased Delivery

Locations and durations of the main phases of the project.